CWPPRA
COASTAL WETLANDS PLANNING, PROTECTION AND RESTORATION ACT
TECHNICAL COMMITTEE MEETING AGENDA
April 19, 2012, 9:30 a.m.
Location:
U.S. Army Corps of Engineers Office
District Assembly Room (DARM)
7400 Leake Avenue
New Orleans, LouisianaDocumentation of Technical Committee meetings may be found at:
http://www.mvn.usace.army.mil/pd/cwppra_mission.htm
- Meeting Initiation 9:30 a.m. to 9:40 a.m.
- Introduction of Technical Committee or Alternates
- Opening remarks of Technical Committee Members
- Request for Agenda Changes/Additional Agenda Items/Adoption of Agenda
- Report: Status of Breaux Act Program Funds and Projects (Gay Browning, USACE) 9:40 a.m. to 9:55 a.m. Ms. Gay Browning will provide an overview of the status of CWPPRA accounts and available funding in the Planning and Construction Programs.
- Decision: Selection of Ten Candidate Projects and up to Three Demonstration Projects to Evaluate for PPL 22 (Brad Inman, USACE) 9:55 a.m. to 10:25 a.m. The Technical Committee will consider preliminary costs and benefits of the 22nd Priority Project List (PPL) project and demonstration project nominees listed below. The Technical Committee will select 10 projects and up to 3 demonstration projects as PPL 22 candidates to be evaluated for Phase 0 analysis, which will be considered later for final selection of projects that will be approved for Phase I (Planning and Engineering and Design).
|
Region
|
Basin
|
PPL 22 Nominees
|
|
1
|
Pontchartrain
|
Small Mississippi River Reintroduction into LaBranche Wetlands
|
|
1
|
Pontchartrain
|
Triangle- Restoring Cypress-Tupelo Swamp & Marsh
|
|
1
|
Pontchartrain
|
New Orleans Landbridge Shoreline Stabilization & Marsh Creation
|
|
2
|
Mississippi River Delta
|
Pass a Loutre Crevasse
|
|
2
|
Mississippi River Delta
|
Pass a Loutre Hydrologic Restoration
|
|
2
|
Breton Sound
|
Lake Lery Marsh Creation & Terracing
|
|
2
|
Breton Sound
|
Terracing & Marsh Creation South of Big Mar
|
|
2
|
Barataria
|
Elmer’s Island Restoration
|
|
2
|
Barataria
|
Northeast Turtle Bay Marsh Creation & Critical Area Shoreline Protection
|
|
2
|
Barataria
|
Bayou Dupont Sediment Delivery – Marsh Creation 3
|
|
3
|
Terrebonne
|
North Catfish Lake Marsh Creation
|
|
3
|
Terrebonne
|
Lake Tambour Marsh Creation
|
|
3
|
Terrebonne
|
Grand Bayou Freshwater Enhancement/Introduction & Terraces
|
|
3
|
Atchafalaya
|
West Wax Lake Wetlands Diversion
|
|
3
|
Teche-Vermilion
|
South Little Vermilion Bay Terracing & Planting
|
|
3
|
Teche-Vermilion
|
Cote Blanche Freshwater & Sediment Introduction & Shoreline Protection
|
|
4
|
Calcasieu-Sabine
|
Cameron Meadows Marsh Creation & Wetland Restoration
|
|
4
|
Calcasieu-Sabine
|
West Cove Marsh Creation & Nourishment
|
|
4
|
Mermentau
|
East Pecan Island Marsh Creation – Increment 1
|
|
4
|
Mermentau
|
Front Ridge Freshwater Introduction & Terracing
|
|
|
Coastwide
|
Coastwide Competitive Voluntary Canal Backfilling
|
|
PPL 22 Demonstration Project Nominees
|
|
DEMO
|
Hay Bale Demo
|
|
DEMO
|
Reconnection of Hydrologically Isolated Wetlands
|
|
DEMO
|
CREPS: Coastal Restoration & Energy Production System
|
|
DEMO
|
Bioengineering of Shorelines & Canal Banks using Live Stakes
|
- Report: Draft 2012 Report to Congress (Karen McCormick, EPA) 10:25 a.m. to 10:30 a.m. Ms. Karen McCormick will present the draft 2012 Report to Congress. The U.S. Geological Survey (USGS), U.S. Fish and Wildlife Service (USFWS), and U.S. Environmental Protection Agency (EPA), and Coastal Protection and Restoration Authority (CPRA) have been leading the 2012 Report to Congress efforts.
- Discussion: Initial Discussion of FY13 Planning Budget Development (Process, Size, Funding, etc.) (Brad Inman, USACE) 10:30 a.m. to 10:45 a.m. The FY13 Planning Program Budget development, including the PPL 23 Process, will be initiated.
- Report/Discussion: Decision Structure for Projects Reaching 20-Year Life Span (Brad Inman, USACE) 10:45 a.m. to 10:55 a.m. At the October 13, 2011 meeting, the Task Force directed the Technical Committee to develop a decision structure (a course of action for the CWPPRA Standard Operating Procedure) to be used as a tool for making logical decisions for projects reaching their 20-year life span. The Planning & Evaluation (P&E) Committee will report on their ongoing efforts with the decision structure.
- Report/Discussion: Standard Operating Procedure for Project Transfers Between Federal Agencies (Brad Inman, USACE) 10:55 a.m. to 11:05 a.m. At the June 8, 2011 meeting, the Task Force directed the Technical Committee to develop a standard operating procedure to address the situation where a project is transferred from one Federal Sponsor to another. Draft language has been presented to the committees. Mr. Brad Inman will present an updated draft that incorporates the P&E Committee’s comments.
- Discussion: Transfer of the PPL 12 — Avoca Island Fresh Water Diversion and Land Building Project (TE-49) (Britt Paul, NRCS) 11:05 a.m. to 11:15 a.m. The landowner of the PPL 12 — Avoca Island Fresh Water Diversion and Land Building Project (TE-49) requests to transfer this project from the current federal sponsor, the US Army Corps of Engineers (USACE), to another agency. The project’s construction has been delayed due to challenges with the cost share agreement.
- Report: Status of the PPL 1 – West Bay Sediment Diversion Project (MR-03) (Nick Sims USACE) 11:15 a.m. to 11:30 a.m. Mr. Nick Sims will provide a status update on the West Bay Work Plan and Closure Plan.
- Decision: Request for a Change in Scope for the PPL 16 — Madison Bay Marsh Creation and Terracing Project (TE-51) (Dr. John Foret, NMFS) 11:30 a.m. to 11:40 a.m. The National Marine Fisheries Service (NMFS) and CPRA request a project scope change to proceed with the design to 30% and 95% for the Madison Bay project. The project location is proposed to be moved 3 miles to the northeast. The net acres restore dare estimated at 470 acres, while the original concept was targeting 688 net acres restored. The NMFS and CRPA also request a cost estimate increase from the original $32,353,377 to an estimated $38,798,788. No additional funds are needed to complete phase 1 of this project. The Technical Committee will vote on a recommendation to the Task Force to approve the request scope change for the Madison Bay Marsh Creation and Terracing Project (TE-51).
- Decision: Request for Approval to Initiate Deauthorization of the PPL 10 — Benneys Bay Diversion Project (MR-13) (Scott Wandell, USACE) 11:40 a.m. to 11:45 a.m. USACE and the CPRA are requesting formal deauthorization procedures be initiated for the Benneys Bay Diversion Project (MR-13) based on the high cost of dredging associated with the project. At the December 13, 2012 meeting, the Technical Committee recommended to “suspend” this project; however, the Task Force did not approve the recommendation for a suspension category. The Technical Committee will vote on a recommendation to the Task Force to initiate deauthorization of the Benneys Bay Diversion Project (MR-13).
- Additional Agenda Items (Tom Holden, USACE) 11:45 a.m. to 11:50 a.m.
- Request for Public Comments (Tom Holden, USACE) 11:50 a.m. to 11:55 a.m.
- Announcement: Date of Upcoming CWPPRA Project Meeting (Brad Inman, USACE) 11:55 a.m. to 12:00 p.m. The Task Force meeting will be held June 5, 2012 at 9:30 a.m. at the Estuarine Fisheries and Habitat Center, 646 Cajundome Blvd., Lafayette, Louisiana.
- Announcement: Scheduled Dates of Future Program Meetings (Brad Inman, USACE) 12:00 p.m. to 12:05 p.m.
|
2012
|
|
April 19, 2012
|
9:30 a.m.
|
Technical Committee Meeting
|
New Orleans
|
|
June 28, 2012
|
9:30 a.m.
|
Task Force
|
Lafayette
|
|
June 5, 2012
|
|
|
|
|
September 12, 2012
|
9:30 a.m.
|
Technical Committee Meeting
|
Baton Rouge
|
|
October 11, 2012
|
9:30 a.m.
|
Task Force
|
New Orleans
|
|
November 14, 2012
|
7:00 p.m.
|
PPL 22 Public Comment Meeting
|
Abbeville
|
|
November 15, 2012
|
7:00 p.m.
|
PPL 22 Public Comment Meeting
|
New Orleans
|
|
December 12, 2012
|
9:30 a.m.
|
Technical Committee Meeting
|
Baton Rouge
|
- Decision: Adjourn